Mr. Conroy updated the committee on construction. Since the last meeting the blasting contractor was mobilized, and as of last Friday, demobilized the blasting contractor, concluding phase 1 with 23 blasts. The rock crusher has been mobilized to create structural fill from the blasted and excavated site rock.

The team plans to utilize school break week to get most of the remainder of the overburden soils off site. We expect to begin preparations for foundations and the delivery of form materials in the next couple weeks, weather permitting. Eversource is currently scheduled to perform work for the temporary power during school vacation.