Weekend work and possible Labor Day weekend work | Aug. 25, 2023

Weekend work and possible Labor Day weekend work | Aug. 25, 2023

The tight building schedule has been exacerbated due to delays related to some trenches at the base of the foundation, which contained asbestos. Due to the location of the asbestos, the delay impacted the site work and paving for the main entrance, which is critical for the first day of school scheduled on Sept. 5.

The team has had to work on Saturdays to make up for lost time. Given the previous delays and recent poor weather, the team will need to work the next two Sundays and (depending on the timing and weather) potentially Monday, Sept. 4. The weekend work will be between 8 a.m. and 4 p.m.